The Project
The new £40 million Estonia National Museum—completed in 2016—signals a new era in construction for the country—combining contemporary museum design elements and sustainability with cultural significance.
Designed by Dorell Ghotmeh Tane architects and built by Fund Ehitus OU, the 34,000m2 building will play a key role in the regeneration of Tartu—Estonia’s second largest city. The arts building will be home to over a million artifacts, which celebrate the history, traditions and culture of Estonia.
Built on the site of a former Soviet military base, the new building’s basement is subjected to 4-5 metres of hydrostatic water pressure and has extensive (30,000) penetration points from reinforcement bars and pipes.
To ensure the basement remains dry and keeps the historical artifacts and artworks at a consistent temperature and relative humidity – a proven waterproofing system was a prerequisite for the museum design.
With long term waterproofing performance, reliability and success at challenging projects worldwide—PREPRUFE® waterproofing offered the ideal protection for the museum’s 6-metre deep basement filled with artworks and culturally significant artifacts.
PREPRUFE® is an advanced membrane system, designed with synthetic adhesive layers and GCP’s patented ADVANCED BOND TECHNOLOGY™.
It enables concrete to aggressively adhere to the PREPRUFE® membrane, forming a unique intimate seal which prevents any water migration between the waterproofing and the structure, reducing the risk of leaks and improving sustainability.
No other system on the market protects a substructure from the harmful effects of water, vapour and gas better than the PREPRUFE® system.
The Process
Utilising an advanced acrylic surface coating developed by GCP, the PREPRUFE® membrane also simplifies the installation process by removing multiple layers and complicated detailing. Protective layers of concrete or boards are eliminated, reducing the depth of excavation, and spoil, while the number of materials to be sourced are minimised, all accelerating the critical path of the project programme.
GCP supplied a range of complementary products and systems to improve the museum design including BITUTHENE® 4000S self-adhesive HDPE waterproofing membrane and BITUTHENE® LM asphalt modified liquid membrane. BITUSTIK™ 4000 double-sided tape was also supplied to complete the project’s comprehensive waterproofing specification.
Blue360sm Product Performance Advantage.
Because every project, large or small, deserves the best level of protection.
gcpat.hk | For technical information: asia.enq@gcpat.com
GCP Applied Technologies Inc., 2325 Lakeview Parkway, Alpharetta, GA 30009, USA
GCP (Hong Kong) Ltd., 6 On Chuen Street, On Lok Tsuen Ind Area, Fanling, Hong Kong
This document is only current as of the last updated date stated below and is valid only for use in Hong Kong. It is important that you always refer to the currently available information at the URL below to provide the most current product information at the time of use. Additional literature such as Contractor Manuals, Technical Bulletins, Detail Drawings and detailing recommendations and other relevant documents are also available on www.gcpat.hk. Information found on other websites must not be relied upon, as they may not be up-to-date or applicable to the conditions in your location and we do not accept any responsibility for their content. If there are any conflicts or if you need more information, please contact GCP Customer Service.
Last Updated: 2023-07-14